Beach Renourishment Now in Progress

[December 15, 2008] - Galveston Island's seawall is about to get a much-needed facelift. Islanders and visitors will begin seeing about 50 sand hauling trucks make their way down Seawall Blvd. this week transporting the first loads of sand for Galveston’s emergency sand placement project. The project is slated to place sand on Galveston beaches from 10th Street to 61st Street.

The goal of the project is to place 400,000 to 500,000 cubic yards of beach quality sand along the seawall. Sand is collected from East Beach, Stewart Beach and dredge material excavated from ocean waters in the Gulf of Mexico. The sand collected from these specific areas will be hauled to create access ramps by means of the existing county ramps (i.e. 29th, 35th, 47th, 57th, etc…).

Sand will then be dumped five feet high and 230 feet out from the Seawall onto the beach beginning at 61st Street and heading east. The movement of the placed sand will build up a sandbar for the sand to move back and forth and continuously stay on the beach.

MAYBE we can see some of this on the webcams!

Link to comment
Share on other sites

Archived

This topic is now archived and is closed to further replies.

  • Forum Jump
    • Categories
      • Welcome to Cruise Critic
      • Hurricane Zone 2024
      • New Cruisers
      • Cruise Lines “A – O”
      • Cruise Lines “P – Z”
      • River Cruising
      • ROLL CALLS
      • Cruise Critic News & Features
      • Digital Photography & Cruise Technology
      • Special Interest Cruising
      • Cruise Discussion Topics
      • UK Cruising
      • Australia & New Zealand Cruisers
      • Canadian Cruisers
      • North American Homeports
      • Ports of Call
      • Cruise Conversations
×
×
  • Create New...

If you are already a Cruise Critic member, please log in with your existing account information or your email address and password.